Our scheduling team has concerns that a SSCAN might be skipped if during the time change, that we spring past the next SSCAN time.
Is this an issue that we need to worry about?
Environment
Release : 11.3, 12.0, 12.1
Component : CA-7
Resolution
There are no problem with daylight savings time and setting the time forward. SSCAN will not miss any jobs because it is already ahead anyway. So, just let CA 7 run as usual.