Cost calculated for team even when there is no rate defined in rate matrix

book

Article ID: 145029

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

When a team has a no rate defined in the Rate Matrix, the 'populate from assignments' on the cost plans still calculates a forecast cost for the team. The article describes how this cost is calculated. 

Environment

Release : 15.7

Component : CA PPM SAAS PROJECT MANAGEMENT

Resolution

To calculate the team rate the cost plan was picking up a row from rate matrix that has all '*' in the columns, this is sort of a 'catch-all' row.  





If that was not the case and if there was no rate association in the rate matrix, then when you were populating the cost plan ( 'populate from task assignments' ) we would land with an error "REVMGR-20728: Rates and Costs are both missing for one or more roles/resources". 

Additional Information

“Since a team is a resource, you can select it for the Resource column in a cost and rate matrix. Set up the financial properties on the team resource profile and go into the matrix that has the Resource column configured and you can select the team resource.”

https://techdocs.broadcom.com/content/broadcom/techdocs/us/en/ca-enterprise-software/business-management/clarity-project-and-portfolio-management-ppm-on-premise/15-7/using/getting-started-with-the-new-user-experience/Manage-Resources-and-Teams.html