Does a Project manager have to accept a resource manager's hard book?
book
Article ID: 144623
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
Once a hard book has been set by the resource manager for a resource, does the project manager have to accept it?
Environment
Release : All Supported Releases
Component : CA PPM SAAS PROJECT MANAGEMENT
Resolution
No, if the Resource Manager has booked the resource as hard, then the Project Manager doesn’t have to accept.
It is recommended the project manager check for any allocation or date changes needed, and if yes, then the booking status changes to mixed and the Resource Manager would approve the changes by changing the status back to Hard.