OWB Not Showing Correct Rates
search cancel

OWB Not Showing Correct Rates

book

Article ID: 144407

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

One the following symptoms may be observed:
  1. Open Workbench is showing a rate of $1 for every resource instead of their correct rate.
  2. No billing rate comes through in OWB, although that rate is present in the rate matrix, it is blank in OWB
Note: The Rate Matrix Extraction job is scheduled to run every 15 minutes, but the rates in OWB have not updated

Environment

Release : All Supported Releases

Component : CA PPM OPEN WORKBENCH (OWB)

Resolution

The Rate Matrix job needs to run to update the rates in OWB, but it needs to run with the first three options checked: 
  •    Extract Cost and Rate Information for the Scheduler 
  •    Prepare Rate Matrix Data 
  •    Update Rate Matrix Data 
Once the job completes, Open Workbench will show the correct rates.

Additional Information

See KB: 141061 for tips on how to optimize use of Self Service for Clarity PPM