  • Planned Internal Rate of Return (IRR) is showing blank in 15.5 and lower.
  • Planned IRR for ideas is not calculating a value and is blank in certain scenarios where costs preceeds benefits by about one year.

    The behavior is limited to detailed plans for ideas; simple plans do successfully calculate IRR.

Environment

Release : 15.4.1

Component : CA PPM PORTFOLIO MANAGEMENT

Resolution

This issue is resolved in Clarity 15.5.1 and higher. See more details in the 15.5.1 Change Impact and Upgrade documentation at:
Internal Rate of Return (IRR) Adjustment (Excerpt below)

Upgrade Action

  • No action is required; however, we recommend that you examine your ideas in Classic PPM. Previously blank values for Planned IRR might now calculate a value as a result of this adjustment in 15.5.1.
  • If no positive (or negative) cash flow exists, IRR is left blank.