Issue/Introduction

If anyone wants to create or edit a project baseline, it requires “Project Modify Baseline” access right  even if project creator (project manager)?

Environment

Release : 15.6.x, 15.7.x

Component : CA PPM APPLICATION

Resolution

In order to create or edit a project baseline, need both project edit access right and also "Project Modify Baseline" access right.