Issue/Introduction
If anyone wants to create or edit a project baseline, it requires “Project Modify Baseline” access right even if project creator (project manager)?
Environment
Release : 15.6.x, 15.7.x
Component : CA PPM APPLICATION
Resolution
In order to create or edit a project baseline, need both project edit access right and also "Project Modify Baseline" access right.