The milestones, which are set for the next week, do not get displayed in Status tab only on Sunday, when a project is opened in New UI
Steps to reproduce:
Expected Results: The 2 milestones will show up in the STATUS tab in the "Next 2 weeks" calendar view.
Actual Results: The milestone, which is in the next week, does not show in the "Next 2 weeks" calendar view.
Workaround: The issue happens only on Sunday.
Release : 15.6, 15.6.1, 15.7, 15.7.1
Component : CA PPM PROJECT MANAGEMENT
Due to defect DE52791.
The Development team is looking into this. Hopefully this would be fixed in one of the upcoming releases of Clarity PPM.