Resource Allocation % on Team incorrect after running Allocate from Estimates
book
Article ID: 143257
calendar_today
Updated On:
Products
CLARITY PPM FOR ITG
CLARITY PPM FEDERAL
Clarity PPM On Premise
Issue/Introduction
I ran the Allocate from estimates action on the project. However, it's not updating the team member allocation correctly for certain date ranges.
Cause
- This can be due to the allocation being prior to the team member's Actual thru date.
- The allocate from estimates action does not update any data prior to the user's actual thru date on the project.
Environment
Release : All Supported Releases
Component : CA PPM RESOURCE MANAGEMENT
Resolution
Manually update the allocations for the time frames prior to the team member's Actual Thru date.
Additional Information
See KB: 51149 - How does 'Allocate from Estimate' calculate allocation?
See KB 141061 - How to search for known Clarity PPM Issues using Self Service