Issue/Introduction

I ran the Allocate from estimates action on the project. However, it's not updating the team member allocation correctly for certain date ranges. 

Cause

  • This can be due to the allocation being prior to the team member's Actual thru date.
  • The allocate from estimates action does not update any data prior to the user's actual thru date on the project. 

Environment

Release : All Supported Releases

Component : CA PPM RESOURCE MANAGEMENT

Resolution

Manually update the allocations for the time frames prior to the team member's Actual Thru date.

Additional Information

See KB: 51149 - How does 'Allocate from Estimate' calculate allocation?