I ran the Allocate from estimates action on the project. However, it's not updating the team member allocation correctly for certain date ranges.
Release : All Supported Releases
Component : CA PPM RESOURCE MANAGEMENT
Manually update the allocations for the time frames prior to the team member's Actual Thru date.