Issue/Introduction

I ran the Allocate from estimates action on the project. However, it's not updating the team member allocation correctly for certain date ranges. 

Environment

Release : All Supported Releases

Component : CA PPM RESOURCE MANAGEMENT

Cause

  • This can be due to the allocation being prior to the team member's Actual thru date.
  • The allocate from estimates action does not update any data prior to the user's actual thru date on the project. 

Resolution

Manually update the allocations for the time frames prior to the team member's Actual Thru date.

Additional Information

See KB: 51149 - How does 'Allocate from Estimate' calculate allocation?