We have an issue with a project. We had accidentally baselined all tasks. Is there any possibility to restore baseline values from Excel table or any other way?
Component : CA PPM PROJECT MANAGEMENT
Normally it is not possible to restore a baseline.
You may be able to reset the baseline dates back if you have a saved copy of Open Workbench and then save that back. The dates and baseline costs will revert. Actual hours and ACWP will not change.