How can I reuse an existing Agile Integration /Agile System in Clarity PPM?
search cancel

How can I reuse an existing Agile Integration /Agile System in Clarity PPM?

book

Article ID: 143125

calendar_today

Updated On:

Products

Clarity PPM SaaS

Issue/Introduction

  1. Is it possible to reuse an Agile Central “systems” that I created in Clarity Integrations and use it for other agile projects in the same workspace? 
  2. If so, how is this done? 

Environment

Release : All Supported Releases

Component : CA PPM SAAS RALLY

Resolution

If you do not want to sync the current projects that are using the Agile System anymore, it is okay to recycle the Agile System. 

IMPORTANT: However, before doing that, make sure the sync flag for these projects is unchecked in Clarity PPM.

Example:

  1. You have Project A - Agile System ABC (Project ID A123) - Sync checked
  2. Now you want to use Project B with Agile System ABC (changing Project ID to B123) - providing Project B was not sync'd before.
  • Uncheck the sync flag on Project A (do it for all projects using this Agile System)
  • Change Agile System Default Agile Central Project Id to B123 (See KB 138550 for help on setting this ID)
  • Change Project B to point to Agile System ABC and check the sync flag

 

Additional Information

See KB 141061 - How to search for known Clarity PPM Issues using Self Service