In the Modern UX for some projects certain task names display blank.
Release : 15.4.1
Component : CA PPM PROJECT MANAGEMENT
This issue will occur if the Summary tasks are showing as Milestones instead of Phases in the Modern UX. To get the Summary tasks names to appear in the Modern UX task list as expected, complete the following steps:
1. Open affected project in the PPM Gantt
2. Add Milestone attribute via Configure option
3. Expand the Summary task that is also a Milestone
4. Outdent the subtasks underneath it to make the Summary task no longer be a Summary task
5. Update Milestone from Yes to No and click Save
6. Indent the child tasks back under the Summary task