We are upgrading our UIM 8.5 env to 9.2.0 and also wish to make use of the latest MCS enhanced profile for Processes

What is correct migration path for this?

Environment

Release : 9.2.0

Component : UIM - MON_CONFIG_SERVICE

Resolution

Existing Processes MCS template versions

  • Setup Processes 1.16.1
  • Processes 2.47.1

Steps

  1. complete upgrade to UIM 9.2.0
  2. download processes probe 4.64 to archive
  3. download processes_mcs_templates 4.65 to archive
  4. deploy processes_mcs_templates 4.65 to primary hub
  5. activate template package as per Migrating and Converting Existing Profiles
  6. Enhance the legacy profile as per Migrating and Converting Existing Profiles