If the task is updated in Clarity PPM, and does not have assignments, if you update the task’s % Complete to something greater than 0, it changes back to 0% in Microsoft Project (MSP)
STEPS TO REPRODUCE:
Expected Results: Task % Complete is 100% in MSP
Actual Results: Task % Complete is 0% in MSP
Note: Additional symptoms for tasks where >0% Complete but less then 100%:
This issue is caused by DE52504
Release : 15.7, 15.7.1
Component : Clarity PPM Microsoft ProjectThis issue is fixed in Clarity PPM 15.8.
Workarounds: