What fields can be mapped between Clarity PPM and Rally?

book

Article ID: 141857

calendar_today

Updated On:

Products

STARTER PACK-CLARITY PPM Clarity PPM SaaS

Issue/Introduction

  • Is it possible to add more attributes for syncing purpose between Agile Central (Rally) and Clarity PPM?
  • Where are fields mapped to for a project/task in Clarity?

Environment

Release : 15.6

Component : CA PPM SAAS RALLY

Resolution

The attributes that are mapped between Clarity and Rally are listed at: Clarity PPM and Agile Central Attribute Mapping

  • This page shows both project level and task level attributes that are mapped
  • In order for task related data to sync, Create and Sync tasks has to be checked in Administration->General Settings->System Options-Integration Link->Integration Policy

Some notes from the documentation highlighted below:

Project Level Attribute mapping:

  • The applicable CA Agile Central Initiative attributes are synchronized back to the CA PPM project Agile Summary page.
  • The Agile Summary page is accessible from the Properties menu for a project

Task Level Attribute mapping:

  • The applicable Task level data from Agile Central is synced back to Clarity PPM's task Agile Summary page.
  • The Agile Summary page is accessible from the Properties menu for a project task.
  • Depending on whether a task in Clarity PPM is synchronized with a feature or a user story in CA Agile Central, the corresponding Agile Summary page appears for the task with the relevant attributes.

Additional Information

  • See 141061 - How to search for known Clarity PPM Issues using Self Service
  • See KB: 18799 To submit an enhancement requesting an improvement/change in the behavior