Can't find task in wip table

book

Article ID: 140673

calendar_today

Updated On:

Products

Clarity PPM On Premise

Issue/Introduction

 There are actuals against the task which were posted from a timesheet, but they don't show up in the ppa_wip table.

Have run post financials process and post to wip processes and that didn't help. Also don't any issues in the invalid transactions table.

 

 

Cause

If you do not see the records in Invalid Transactions it normally means either


1) Project is not financially enabled


2) Resource is not financially enabled and financially active


3) Project Financial Status is not Open



Environment

Release : 15.5

Component : CA PPM FINANCIAL MANAGEMENT

Resolution

1) Project is not financially enabled - Financially enable project

2) Resource is not financially enabled - Financially enable resource and  make sure Financially Active checkbox is clicked

3) Project Financial Status is not Open - Change Financial Status to Open


Then run Post Timesheets job again.

The job will check to see if any previously posted timesheets have a change in financial status and will process those through to Invalid Transactions for further financial processing  (Post Transactions to Financials and Post to WIP.)

Additional Information

Posted TS not in PPA_WIP - how to process it to ppa_wip?

https://community.broadcom.com/communities/community-home/digestviewer/viewthread?MID=750392#bmcc1fc98a-4239-43b2-8332-c4a137cb24b7



How is PRRMEXPORTED field on PRTIMEENTRY updated?

https://community.broadcom.com/communities/community-home/digestviewer/viewthread?MID=727707