We ran allocate from estimates by mistake and allocations updated. We want all allocations to be 0. How can we do this?
Ran allocate from estimates by mistake
Release : 15.4
Component : CA PPM RESOURCE MANAGEMENT
For each project you can use the Action Set Allocation .
Here you can remove all allocations by selecting resources from the team page and going to Actions/Set Allocations and setting Default Allocation = 0.00% and then checking the box to Clear existing allocation segments.
Refer to
https://techdocs.broadcom.com/content/broadcom/techdocs/us/en/ca-enterprise-software/business-management/clarity-project-and-portfolio-management-ppm-on-premise/15-7/using/getting-started-with-classic-ppm/project-management/manage-project-teams/manage-resource-allocation.html#concept.dita_e4c13654afdbd94b94ec2df4bfe510a905854cf2_SetResourceAllocationforMultipleStaffMembers
For additional information.