Dates for Financial Plan are not updated by XOG when the specified dates are greater than 01/Jan/2070.

book

Article ID: 140232

calendar_today

Updated On:

Products

CA Project & Portfolio Management

Issue/Introduction

When running XOG to update the Financial Date with the dates greater than 1/Jan/2070, it seems it completes successfully without an error message. However, the dates are not updated as expected.

Cause

Limitation

Environment

Release : ALL

Component : CA PPM APPLICATION ADMIN, STUDIO, XOG & PROCESSES.

Resolution

At this point, 2070 is still 50 years in future. Currently on Clarity PPM, it is recommended to track projects beyond 10 years because just increasing the Financial Plan date, such as Cost Plan date, does not help to without increasing Timslices. Generally, we highly recommend to extend the Timeslices for future 3 years and maximum 5 years. If you increase the Timeslices further, you may encounter a performance issue.


We will increase the capability to set dates for the future years in a future's release.