STEPS TO REPRODUCE
1. Login to PPM new UX with the admin user
2. Edit a project and go to the tasks tab.
http://<host>/pm/#/project/5007001/tasks
3. Check the board view
Task dates display correctly.
4. Check the timeline view
Tasks display correctly.
5. Logout and login with an user whose language is set to Spanish
6. Check the board view
Task dates are not correctly displayed
7. Check the Timeline view
Tasks are not correctly displayed
Expected results: Task dates to display correctly on board and timeline views when user language is set to Spanish
Actual results: Task dates do not display correctly on board and timeline views when user language is set to Spanish
Release: 15.7