When xogging in team records with allocation, the Allocation takes some time to update, but the Remaining Allocation updates immediately after the XOG completes.
What would be the reason for this?
Release : All releases
Component : CA PPM PROJECT MANAGEMENT
Time Slice job configuration
The Remaing Allocation is a virtual attribute that does not rely on slice data to calculate so it gets updated immediately.
However, the Allocation value is calculated based on allocation slices, and the allocation slices do not update or get created until the Time Slicing job runs. For example, if the Time Slicing job runs once per minute, it would take up to a minute after the XOG for the Allocation amount to update.
Please check how often the Time slicing job is set to run. If values are not being updated at all, the time slicing job might actually be paused.