Issue/Introduction

Steps to Reproduce:

1. Create a project with dates spanning from 01/01/2019 to 31/12/2019

2. Create 10 milestones with different dates:

   Milestone 1 > 15/01/2019

   Milestone 2 > 15/02/2019

   Milestone 3 > 15/03/2019

   Milestone 4 > 15/04/2019

   Milestone 5 > 15/05/2019

   Milestone 6 > 15/06/2019

   Milestone 7 > 15/07/2019

   Milestone 8 > 15/08/2019

   Milestone 9 > 15/09/2019

   Milestone 10 > 15/10/2019

3. On the Modern UX, filter by the project

4. On the project tile you see 10 milestone icons

5. Open the project and check the header area. It displays 10 milestone icons

6. Create one additional milestone:

   Milestone 11 > 15/11/2019

Expected Results: The 11th milestone diamond to display

Actual Results: The latest milestone icon does not display

Environment

Clarity 15.x, 16.x 

Resolution

This is working as designed. The project timeline displays the project start and finish dates and the completion status of the milestones. You can see a maximum of ten milestones from today.

Additional Information

  • If multiple milestones fall on the same day, only one milestone icon is displayed for all views
  • If you have 10 milestones falling on the same day and an additional milestone on a different day, only 1 milestone icon will display 