Issue/Introduction

When clicking on a project in the Modern User Experience (UX), all the Team Tasks & Assignments are calculated along with the rights the user has on the project.

Environment

Release: 15.5.1

Cause

The query is not optimal in the Modern UX. This is caused by DE49702

Resolution

This issue is fixed in Clarity 15.6