Can I run Load Data Warehouse job and Time Slicing job?

book

Article ID: 134388

calendar_today

Updated On:

Products

Clarity PPM On Premise

Issue/Introduction

The time slicing job which populates the task ETC by period does not run while the load data warehouse job is running.  When a user creates a new project from template they need to wait till the load data warehouse is finished before they can begin to work on their project. 

Is there any workaround to force populate the etc's by period on the task so the users do not need to wait so long to begin working on the project?


Environment

Release : 15.5.1


Resolution

The time slice job no longer needs to be set as incompatible to the Load Data Warehouse job.