Why are my ETCs / Estimates being updated for months in the future?
Applies to all supported PAS environments for specified releases.
This can be related to the loading pattern set for the assignment. For example, if loading pattern is set to 'Front', after running the Post Timesheets job, ETCs will be updated to be completed as close to the start of the task as possible.
To keep assignment ETCs from being redistributed for future months, you can set the assignment Loading Pattern to Fixed. However, please note when the Post Timesheets job is run, this loading pattern type will cause any remaining ETC for posted (past) time periods to be be deleted.
To update the loading pattern for one assignment:
To change the default loading pattern for all new assignments: