Cost Plan "Submit for Approval" option missing from New UI without Budget Plan Edit rights
book
Article ID: 132391
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
Steps to Reproduce: 1. Create a user and provide him with All Project rights(global) except the following: Project - Budget Plan - Approve All Project - Budget Plan - Edit All Project - Budget Plan - View All 2. Login using this user to the Classic UI. Create a Project, and create a cost plan 3. Go into the detailed view of this cost plan. Hover over Actions. Notice that "Submit for Approval" option is present 4. Go into the New UI, open the same project. Go to "Financials" tab 5. Go to Cost Plans list view. Click on the three vertical dots at the end of this cost plan row. Notice that the "Submit for Approval" option is not present
Expected Results: "Submit for Approval" option is expected in Step 5
Actual Results: "Submit for Approval" option is not present after Step 5