On the Modern UX, when creating a timesheet using the 'Work To Timesheet' option, All Tasks are displayed by default. The Classic UI, when adding a task, defaults to Assigned Tasks
search cancel

On the Modern UX, when creating a timesheet using the 'Work To Timesheet' option, All Tasks are displayed by default. The Classic UI, when adding a task, defaults to Assigned Tasks

book

Article ID: 132342

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

On the Modern UX, when creating a timesheet using the 'Work To Timesheet' option, All Tasks are displayed by default. The Classic UI, when adding a task, defaults to Assigned Tasks.
Both interfaces should be coherent.

Environment

Release:
Component: PPMTMM

Cause

This has been addressed through DE48885

Resolution

In 15.6.1, both interfaces default to Assigned Tasks when working with timesheets