A user is unable to see the "time-scaled value" (TSV) option from the Options icon for portlets under the 'Workload' and 'Allocations' tabs under Resource Planning in Clarity PPM Production.
Example of portlet with issue:Resource Workloads portlet.
Notes:
- The user can see this option in another PPM environment (Example: Sandbox).
- They have limited views when they go to configure the workloads tab in Prod compared to Sandbox.
- The user is currently using Microsoft Windows 10 and Edge for their browser.
- Tried clearing browser cache in both Edge and IE11.