WIP Adjustment Assignment not created

book

Article ID: 132042

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

 STR.
 
 1. Create a transaction.  Does not matter if there is already an assignment.  It will create it.
 2. Run Import Financial Actuals to see it post back to the task
 3. Create a WIP adjustment to another project (Project B) where the resource has no assignment.
    -   This can be an adjustment on the transaction or a transfer, it does not matter.
   
    -  In my test the resource was not even on the team on the second project but even when I added to the team and still no assignment, the record did not import.
    
4.  Approve the WIP Adjustment
5.  Run Import Financial Actuals
 
 
 

Expected Result: Hours removed from original project and posted to transferred project.
Actual Result:  Hours removed from original project but hours stuck in pac_imp_actuals_export table as it cannot create the assignment.

Cause

This is reported as DE49116 and has to do with how the Import Financial Actuals job processes the adjustments.
 

Environment

Release:
Component: ODTSL

Resolution

This is reported as DE49116 and has to do with how the Import Financial Actuals job processes the adjustments.