Is there a setting in Clarity PPM that would determine how the ETC amounts get rounded on the time scale on task assignments? Is it possible to get the amount to round to the nearest quarter hour (.25, .50, .75, .00)?
Environment
Release: Component: PPRPRM
Resolution
If the ETC hours are entered as a total, PPM will redistribute the total amount of ETC's throughout the entire assignment duration. Unfortunately, it will not round to the nearest quarter hour. It will round depending on what the total amount of ETC's divided by the number of work days ends up being.