Clarity PPM: Rounding of ETC

book

Article ID: 131713

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction



Is there a setting in Clarity PPM that would determine how the ETC amounts get rounded on the time scale on task assignments? Is it possible to get the amount to round to the nearest quarter hour (.25, .50, .75, .00)?

Environment

Release:
Component: PPRPRM

Resolution

If the ETC hours are entered as a total, PPM will redistribute the total amount of ETC's throughout the entire assignment duration. Unfortunately, it will not round to the nearest quarter hour. It will round depending on what the total amount of ETC's divided by the number of work days ends up being.