How is SVC 35/36 used by SMR? Is there an example of what features are involved?
Environment
Release: ESBSMR99000-3.4-Extended Support Basic-for CA SMR Component:
Resolution
SVC 35/36 - SVC 35 and 36 (WTO/WTOR and WTL)
Whenever SVC35and SVC36 is issued SMR gets control (the implanted code in CSA/ECSA) and looks at the actual message to determine whether or not to POST the SMR Started task to do something.
This is determined by your options setting on the activity to take..
For example SMR will check to see if it's time to start the CAPLWTR job. If it is, SMR will POST the SMR started task. SMR actually starts it. SMR checks to see if the IBM writer has completed, if so, we POST the SMR started task so that he can P CAPLWTR (or whatever).