What field in MS Project captures the Clarity "Status" field in the PPM Export?
search cancel

What field in MS Project captures the Clarity "Status" field in the PPM Export?

book

Article ID: 131191

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

What field in Microsoft Project (MSP) captures the "Status" field in the Clarity PPM Export? 

Environment

Release:
Component: ODMSP

Resolution

The Clarity PPM task Status field maps to MSP's % Complete field. As referenced in the below documentation at : MSP: Field Mappings Between MSP and CA Clarity PPM:

The task status is set to "Started" when the percent complete is greater than zero, or to "Complete" when it is 100. Otherwise, this field is set to "Not Started".