MSP New Driver: Not started milestones/tasks in the past change to a different date then what's in PPM
book
Article ID: 130396
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
Not started milestones/tasks that have a predecessor exported to Microsoft Project (MSP) with dates in the past change to a different date then what's in Clarity PPM.
Environment
Release: Component: PPMMSP
Cause
This is working as expected due to MSP behavior. This can be reproduced in MSP standalone. This can happen if the task/milestone has a predecessor and / or no constraint is set. For example, if the task has a start / finish date of 3/21/19 in PPM, but has a Start-Start predecessor that's completed with a start/finish date of 1/8/19, the task start/finish date will export to MSP with a start date of 1/8/19.
Resolution
A few options to work around the behavior:
Add a constraint for the task (see KB000047129 for more details on how to set a constraint)
Add a Lag to the dependency (IE Set the predecessor to '1SS+5 days') to push the date of the task out
Turn 'Calculate project after each edit' of:
In MSP, go to File ->Options
Click on the Schedule link on the left hand side
Under calculation, change Calculate project after each edit to ‘Off’
Click OK.
Notes:
Make sure not to click F9 on the keyboard in MSP as this will autoschedule dates.
This is listed as required to be set to 'On' in working with the MSP New Driver, so be sure to test this out in your projects in non production. Also if you do run into unexpected issues, this setting may need to be turned back on for Broadcom support troubleshooting