Unable to change the start/finish timestamp for a resource on a team under certain conditions
book
Article ID: 130307
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
Unable to change the timestamp for a resource on the team to a later time then 5:00 PM if the team member's finish date is the same as the project finish date.This issue doesn't happen if you are trying to change the timestamp to a later time (example 10:45 PM) for a resource if the resource's finish date on the team tab is less than or greater than the project finish date.
For the start day/time of a resource, the behavior is slightly different, you can’t change the start time to earlier then 8:00 AM on any day that is equal to or less then the project start date. You can change it to earlier in the day (Example 5:00 AM ET) if the start date of the resource is later then the start date of the project).
Steps to Reproduce (using Finish Day/Time): 1. Create a project in Clarity PPM with Start Date of 12/17/2018 and Finish Date of 12/19/2018 2. Add a team member to the project 3. On the Team list view, change the Finish attribute's Date/Time Format Scale to 'Day Time' 4. Change the Finish date/time for the team member to 12/19/2018 10:45 PM 5. Click Save Expected Results: Changes made are saved, the resource's Finish Date / Time is saved as 12/19/2018 10:45 PM Actual Results: The resource's Finish Date / Time is reverted back to 12/19/2018 5:00 PM
Workaround: Change the finish date of the project to be done day later (IE 12/20/2018). If you do this, then you are able to change the resource finish time to 12/19/2018 11:45 PM. However, this then impacts any future resources added to the project, as their finish date will default to 12/20/2018 instead of 12/19/2018.