How does Actual Costs get pulled in to Portfolios?

book

Article ID: 129732

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction



How does Actual Costs get pulled in to Portfolios in Clarity PPM?

Environment

Release:
Component: ODPFM

Resolution

For the Actual Cost field (column) the data included here is actual cost for the investment that falls within the dates set for the portfolio on properties tab. However, the Actual Cost (Total) and the actual cost in any TSVs would display the totals for the entire project length even if the dates are outside the portfolios.

Additional Information

SeeĀ CA PPM Tuesday Tip: Portfolio Investment Attributes