How does Actual Costs get pulled in to Portfolios?
book
Article ID: 129732
calendar_today
Updated On:
Products
CLARITY PPM FOR ITGCLARITY PPM FEDERALClarity PPM SaaS - ApplicationClarity PPM On Premise
Issue/Introduction
How does Actual Costs get pulled in to Portfolios in Clarity PPM?
Environment
Release: Component: ODPFM
Resolution
For the Actual Cost field (column) the data included here is actual cost for the investment that falls within the dates set for the portfolio on properties tab. However, the Actual Cost (Total) and the actual cost in any TSVs would display the totals for the entire project length even if the dates are outside the portfolios.