In tab Time & dependencies, in the section Dependencies, entries are missing in AWI

book

Article ID: 129211

calendar_today

Updated On:

Products

CA Automic Workload Automation - Automation Engine

Issue/Introduction

Add a new Task to a Workflow. Open the Task Properties of the newly added task and switch to tab Time & dependencies:
 

<Please see attached file for image>

User-added image
 
In section dependencies, there is only one check-box, but all the other elements are missing.

Environment

Release: AUTWAB99000-12.2-Automic Workload Automation-Base Edition
Component:

Resolution

Solution: Install a fixed version or a newer one.
  • Automation.Engine 12.2.2
  • Automation.Engine 12.3.0
Workaround: To see these elements, save and close the Workflow. After reopening, these elements are shown.
 

<Please see attached file for image>

User-added image

Attachments

1558688904869000129211_sktwi1f5rjvs16fr8.png get_app
1558688901973000129211_sktwi1f5rjvs16fr7.png get_app