When trying to save a project back from MSP (Microsoft Project) to Clarity, receive Project Save Failed error / the project will not save.
Prior to the Project Save Failed error, you may see error "Summary task assignments are not supported"
Reviewing the app-ca.logs, error indicates issue related to a summary task having an assignment:
ERROR 2019-02-25 13:24:06,577 [https-jsse-nio-443-exec-18] niku.schedulers (clarity:user:session:schedulers.postProject) Rolling back transaction: java.lang.Exception: Summary task configure test environment(null) cannot have assignments.
Release: All Supported Releases
Component: Clarity Microsoft Project Interface
Summary task assignments are not supported in Clarity
You will then see that the Summary task is now converted into a child task (unbolded)
In the error associated with the project, the summary task name will be displayed. Note, that this will only display the first summary task name impacted if there is more than one.