Missing Budget Cost Start or Budget Cost Finish date Error

book

Article ID: 129043

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

When attempting to Inactivate an investment the following error message is generated:

Missing Budget Cost Start or Budget Cost Finish date

Cause

Budget Cost Start or Budget Cost Finish date, are not populated in the investment, it is necessary to populate these fields with the correct information.

Environment

Release:
Component: ODPRM

Resolution

It is necessary to add the fields using XOG in order to resolve this. It will not be possible to make the update using the interface.