Migrated Charge Code on NBI PROJ RES RATES AND COSTS Table
book
Article ID: 127853
calendar_today
Updated On:
Products
CLARITY PPM FOR ITGCLARITY PPM FEDERALClarity PPM SaaS - ApplicationClarity PPM On Premise
Issue/Introduction
What is the migrated charge code in the NBI_PROJ_RES_RATES_AND_COSTS table in CA PPM?
Environment
Release: Component: PPRPRM
Resolution
The charge code will be Migrated in the NBI_PROJ_RES_RATES_AND_COSTS table if there is no charge code set on the task.
PPM knows to check the Charge Code at the project level, if the Charge Code at the Task level is left blank.
Open Workbench also knows to populate the Charge Code at the task level with the Charge Code at the next level up. OWB will also display the inherited charge code, while PPM will not.