Phase Task List Tool Tip in New UX causes tasks to be prematurely marked completed

book

Article ID: 127761

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

In the New User Experience / Modern UX, the Phase Task List has a circle to indicate if a Task is Open or Completed.  The Tool Tip shows 'Open' when it is open and 'Completed' when it is marked Completed.  The Tool Tip should be the same as what is shown on the Task Board 
  • When the Task is Open, the Tool Tip should show 'Mark Complete'
  • When the Task is Completed, the Tool Tip should show 'Mark Incomplete'
STEPS TO REPRODUCE:
1. Log into Modern UX in Clarity PPM and navigate to the Project TASKS Module - Phase List page
2. Hover over an Open task, the tip shows 'Open'
3. Click to mark it completed 
4. Hover over a Completed task, the tip shows 'Completed'
 
EXPECTED RESULTS: The tool tips should match what we see on the Task Board
ACTUAL RESULTS: The tip of 'Open' and 'Completed' are confusing and cause users to mark open tasks completed prematurely

Cause

This issue is caused by DE47928

Environment

Release: CODFSS99000-15.5-PPM SAAS FedRAMP-Sandbox-Small Environment
Component:

Resolution

This issue is tentatively planned to be fixed in Clarity PPM 15.6.1.