On some projects, when I go to the Financial Plans tab, I do not see the New Manual Plan button. What does govern the button being present or not?

book

Article ID: 126286

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS - Application Clarity PPM On Premise

Issue/Introduction



On some projects, when I go to the Financial Plans tab, I do not see the New Manual Plan button. 
What does govern the button being present or not?
New From Investment Team or New From Assignments actions are not visible either.
Why are these actions available on some projects and not on some others?

Environment

Release:
Component: PPMFNM

Resolution

Cost plan creation/population is governed by the following right:
Project - Cost Plan - Edit All 
Please review the security implementation and ensure the user has got the right for the given projects