Mark completed projects inactive in bulk

book

Article ID: 125546

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

We have around 1500 projects that are completed but still active and want to mark them as inactive.  Is there an easy way to do this in bulk?

Environment

Release:
Component: ODBPM

Resolution

There is no out of the box solution for inactivating projects in bulk. You could come up with custom solution via process utilizing GEL/XOG for looping through those projects and updating it via XOG. You also could create a process using system action that updates Active attribute based on custom attributes that you should set which will trigger your process, something like is_complete (Boolean type).