Issue/Introduction
I would like to know where Data Warehouse fields in DWH_INV_SUMMARY_FACTS come from: EAC_TOTAL_COST ACTUAL_COST
Environment
Release: Component: ODDWH
Resolution
DWH_INV_SUMMARY_FACTS table:
EAC_TOTAL_COST Total estimate at completion cost from assignments. It will take and add data from the combined assignments on the investment.
ACTUAL_TOTAL_COST Total actual cost from financial transactions. ACTUAL_LABOR_COST Actual cost from financial transactions where the transaction type is Labor. ACTUAL_LABOR_HOURS Actual labor hours from assignments.
The data gets collected from Assignments, and then summarized to Investment level.