How to make XOG-IN for task and project baseline.

book

Article ID: 124974

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS - Application Clarity PPM On Premise

Issue/Introduction



I check prj_projects_write.xml and find the following description so that this includes task baseline start date, baseline finish date and baseline workload 

『This project has sample data for all attributes (that can be set through XOG) of task, project Team and assignment』

Then please let me know the way how to make XOG-IN for task and project baseline.

Environment

PPM 15.4.1

Resolution

You can make XOG-IN for task and project baseline.
But each has the different definition so that please define as follows. 
  Task baseline : <Baselines> tab 
  Project baseline : <ProjectBaselines> tab