Question about CA11 Option OPCORCT
search cancel

Question about CA11 Option OPCORCT

book

Article ID: 124193

calendar_today

Updated On:

Products

Workload Automation Restart Option for z/OS Schedulers (CA 11)

Issue/Introduction



Can the OPCORCT for CA 11 be overridden by some other option, or possibly by a CA7 option? 

Environment

Release:
Component: 11

Resolution

When using CA 7 with CA 11, the appropriate PARM is always automatically passed and therefore no WTOR is generated.  This option was an enhancement many years back for customer using CA 11 without a scheduler.  

OPCORCT is not required to be used and you should set the option to 'N', but leaving it to Y is not going to cause problem.