After changing the shift of a day marked as "Workday (Base Calendar)" for a resource, the day is kept as "Workday (Base Calendar)", not "Workday (Exception)".
Steps to Reproduce
Expected behavior: The day appears as Workday (Exception).
Actual behavior: The day appears as Workday (Base Calendar).
Any Clarity PPM release.
This is expected. The exceptions are related to the fact that a day that it is a Workday in the base calendar and a Non-Workday for a resource calendar, or the other way around.
This is not taking into account if there is a difference in the shift between the base calendar and the resource calendar.