We have got a process that sends an Action Item and after its approval, the process contains a System Action that updates a project field to a given value.
In the audit trail I see the updated by as the user who started the process, opposed to the one who responded to the Action Item. Is this correct?
Any supported Clarity release
The System Action is performed by the process initiator.
If a process updates an attribute through a system action that will done under the user who started the process.
The Audit Trail will show the process initiator as the one who performed the change and not the user who approved the Action Item