Resource assignment ETC is not adjusting based on changes made to the Resource calendar or updated allocations if the resource was assigned to the task before the calendar/allocation change was made in Clarity PPM. This calendar change includes marking days set as working days as non working days., the allocations on the team can be changed by the periods or the default allocation.
Release: Any Supported Release
Allocations are tied to availability and will automatically update when the resource's calendar changes.
ETC previously defined are not affected by changes to calendar or allocations as the work will still need to be completed in the defined work period. Reports and portlets will show that the resource is now over assigned for this period.
Note: Any task assignments on Custom Investment Types (CIT) don't have autoscheduling capabilities, so this must be updated manually