Issue/Introduction
When adding work to a timesheet, the following error is displays: TMA-1003: Resource assignment is either invalid or there is already an existing time entry for the assignment: Resource ID
Environment
Release: Any
Cause
This is due to a project team or task configuration issue.
Resolution
The error can occur if the resource is not assigned to the task and the task status is 'Completed'
Check to ensure the following is set:
Is the resource a team member of the project? If not, assign them to the task, OR
Change the project task status to 'Not Started' or 'Started' if not already set.