What is the Runtime of jobs in forecast if the Job runtime is set as fixed value in Runtime tab?
Environment
Release: Component: AAUTEN
Resolution
The forecast always takes the "current ERT" for the forecast calculation. Even if a fixed value is set, this value is used for future executions of the task but not the forecast. If a customer wants to use the fixed value, the ERT calcluation has to be reset first and after the next exeuction, the fixed value is also the "current ERT".