When I delete Milestones from Agile Central they are being kept the CA PPM Project: <Project Name> - Properties - Main - Agile Summary page.
STEPS TO REPRODUCE:
- Create an Agile Central integration in CA PPM with “Create Direction: Agile Central to PPM”
- Create a new Project in CA PPM and navigate to the CA PPM Project: <Project Name> - Properties - Main - Agile Summary page
- Input the integration created in Step 1 within the “Agile System”
- Check the checkbox “Synchronize”
- Click Save
- Click on the “Actions” dropdown at the top right
- Click on “Synchronize Agile Central” to create the initiative from the Agile Central side
- Navigate to the Agile Central Environment
- Click on the Initiative ID to bring up the Initiative’s information
- Add one or two Milestones
- Click the Save button
- Navigate back to CA PPM and navigate to the Agile Summary page
- Click on the “Actions” dropdown at the top right
- Click on “Synchronize Agile Central” to sync the initiative from the Agile Central side
- Navigate to the Agile Central Environment
- Click on the Initiative ID to bring up the Initiative’s information
- Remove all Milestones currently added
- Click the Save button
- Navigate back to CA PPM and navigate to the Agile Summary page
- Click on the “Actions” dropdown at the top right
- Click on “Synchronize Agile Central” to sync the initiative from the Agile Central side
EXPECTED BEHAVIOR:
All Agile Milestones should be deleted from the CA PPM Project: <Project Name> - Properties - Main - Agile Summary page
ACTUAL BEHAVIOR:
The last Agile Milestone added from the Agile Central side is retained in the CA PPM Project: <Project Name> - Properties - Main - Agile Summary page