If team member is open for time entry, what else is required in New UX?
book
Article ID: 112964
calendar_today
Updated On:
Products
Clarity PPM On Premise
Issue/Introduction
It seems Open for Time entry is not working in the New UI, am I missing something required for the user to track time?
1. Open New User Experience (UI/UX) Resource page 2. Select a resource 3. Click on an investment the resource is allocated to to open the 'Detail' tab 4. Check "Open for Time Entry"
Environment
Release: All Supported Releases Component: ODPRM
Cause
This can be due to not all requirements being set for a user to track time on a project
Resolution
Ensure that the project is open for time entry as well in order to track time.
In the New UX, go to the Project DETAILS tab then SETTINGS
THE 'Open For Time Entry' in the project 'SETTINGS' section in the New UX determines whether or not a project is Open for Time Entry.